Sub-Contractor Audit Checklist

Before the audit
Pre-audit preparation:
- Audit scope. Which trade or work package, which stage of work, which standards apply, what areas of the site.
- Document review. The sub-contract, the project ITP for this trade, the relevant Australian Standards, prior audit reports, prior NCRs, the trade's own QA records, any RFI responses affecting the work.
- Programme check. Where is this trade against their programme? Have they mobilised, started, completed?
- Site coordination. Who from the head contractor is attending? Who from the trade? When and where?
- PPE and induction. Standard site PPE, current site induction, any specific trade-area requirements.
A well-prepared audit goes faster on site and produces a sharper report.
On site, the structural checks
- Materials on site match the specification. Brand, grade, size, source. Where alternative products have been used, is the substitution documented and approved?
- Install sequence matches the manufacturer's instructions. Especially relevant for products with strict install protocols (waterproofing membranes, fire-rated systems, structural fixings).
- Hold-points have been inspected and signed off. Each hold-point in the ITP up to this stage should have a corresponding sign-off in the trade's QA record.
- Witness-points have been attended where required.
- Sample testing has been done where the ITP calls for it. Concrete cylinder results, soil compaction tests, water tightness tests, captured and filed.
- The work is in spec for measurable elements. Tolerances on dimensions, levels, finishes. Tape and level used.
- The work is in spec for visual elements. Quality of finish, alignment, integration with adjacent trades.
On site, the documentation checks
- Mill certificates and product certificates for all materials requiring traceability.
- Manufacturer install certificates where the install requires a certified installer.
- Conformance evidence captured at each hold-point per the ITP.
- Trade's own quality records complete, current, filed.
- Prior NCRs addressed, with evidence of close-out.
- As-built documentation matches the installed work.
On site, the workmanship checks
- Setting out and alignment. Lines, levels, plumb where the standard requires.
- Joints and connections. Closed properly, sealed properly, structurally appropriate.
- Edges and terminations. Treated to the standard's requirements (especially relevant for waterproofing, cladding, fire-rated systems).
- Penetrations and interfaces. Where one trade's work passes through another's, the interface meets both trades' specifications.
- Surface finishes. Free from defects that compromise function or aesthetic per the contract.
Trade-specific elements (varies by audit scope)
Different trades have different audit priorities. A few examples:
Waterproofing:
- Membrane brand and grade against specification
- Substrate preparation
- Coverage thickness and continuity
- Termination details (penetrations, junctions, drainage points)
- Manufacturer install certificate
- Water tightness testing record
Structural concrete:
- Reinforcement detailing matches drawings
- Cover and spacing
- Concrete grade and slump per pour record
- Cylinder testing record
- Curing protocol
- Post-tensioning records if applicable
Fire-rated separation:
- System matches the FRL specified
- Penetrations sealed to FRL
- Doors, frames, hardware to specification
- Manufacturer install records for fire-rated systems
- As-built fire compartmentation diagram
Acoustic separation:
- System matches the Rw / DnT specified
- Penetrations sealed for acoustic performance
- No flanking paths around or through the separation
- Test results if commissioning testing is required
The audit report
The audit produces a written report:
- Audit scope and methodology
- Trade and sub-contractor identification
- Conformance findings
- Non-conformance findings with photographs, references, recommended close-out
- Pattern observations
- Assessment of the trade's own QA records
- Overall conclusion
NCRs are issued separately for each non-conformance item, with the report referencing the NCR numbers for the audit trail.
After the audit
- Issue the report to the head contractor.
- Issue NCRs to the trade for each non-conformance.
- Schedule close-out verification. Each NCR gets a follow-up inspection to confirm remediation.
- Update the QA file.
For repeat trades on the project, audit findings feed the risk register and inform the next audit's scope.
Where QBFS conducts sub-contractor audits
QBFS conducts sub-contractor audits on residential, multi-residential, and commercial projects across Australia.